66-inch Water Line Interconnection Along W. Hardy Rd From BW8 to Greens Rd.
Project Number:
TABS2019014088
Facility Name:
West Hardy Rd.
Location Address:
West Hardy Rd Between BW-8 to Greens Rd.
Houston, TX 77060
Location County:
Harris
Start Date:
11/2/2020
Completion Date:
12/23/2021
Estimated Cost:
$225,000
Type of Work:
New Construction
Type of Funds:
This project involves public funds, public land, or is a Federally funded roadway project.
Scope of Work:
Install sidewalk along the northbound lanes of West Hardy Rd. from Beltway 8 to Greens Rd. Also included in this project are installation of a 66" WL and redesign of the northbound lanes.