General Questions
  1. What changes were made to the Industrialized Housing and Buildings law in the 2019 legislative session?
  2. What types of commercial buildings are regulated by the Texas Industrialized Housing and Buildings (IHB) program?
  3. Are there any commercial modular buildings that are not regulated by the IHB program?
  4. Are all portable buildings that are used as classrooms required to comply with the law?
  5. My school district bought or leased non-certified site-built REFs prior to January 1, 2010. Can the school district renew the leases on these classrooms? Can the school district sell these classrooms to be used as classrooms?
  6. What is a "man camp" Are modular buildings constructed for 'man camps' covered by the IHB law and rules?
  7. Is housing covered by the IHB program? What is the difference between an “IHB” or industrialized (modular) house and a manufactured house?
  8. My house has a chassis—doesn’t this mean it’s a manufactured house?
  9. What is the difference between an IHB manufacturer and an industrialized builder?
  10. What is the difference between an IHB manufacturer and a REF builder?
  11. What is the difference between an industrialized builder’s registration and an installation permit?
  12. I am purchasing an industrialized house and want to build my own deck. Do I have to be registered as an industrialized builder?
  13. The local building official says that I need an IHB decal. How do I get one?
  14. Can industrialized housing be installed on a temporary foundation? What is the difference between a "permanent" foundation and a "temporary" foundation?
  15. Chapter 1202 of the Occupations Code adopts the National Electrical Code, the Uniform Building Code group, and the Standard Building Code group as they existed on January 1, 1985, but the construction documents for modular housing and buildings installed within my jurisdiction indicate compliance with a later edition of the National Electrical Code (NEC) and the International Codes (I Codes). Is this legal?
  16. Where can I obtain a copy of the mandatory building codes adopted under the Texas Industrialized Housing and Buildings program?
  17. Can a municipality prohibit buildings constructed under the IHB program from being placed inside their city limits or restrict these buildings to an area zoned for manufactured housing? If not, what authority do the municipalities have over IHB buildings?
  18. How do I transfer the title to my industrialized house or building?
  19. Can I have my portable building recertified if it is altered? Is the altered building required to meet the mandatory building codes currently adopted under the IHB program?
Licensing Questions
  1. Can I apply for an installation permit for the installation of an industrialized house that will then be sold as real estate with the property on which it is installed?
  2. Why do I have to give you my social security number when applying for registration?
  3. Does the Texas IHB program have reciprocity with any other state modular construction program?
  4. How does a manufacturer become a certified (approved) industrialized housing and buildings manufacturer for Texas?
  5. How much does it cost to renew my registration?
  6. Who signs the application for registration for Manufacturers and Builders?
Enforcement Questions
  1. How do I file a complaint against a licensee?
Communication Questions
  1. How may I receive notification of new and changing information with your department?

General Questions

1. What changes were made to the Industrialized Housing and Buildings law in the 2019 legislative session?

Two bills passed in 2019 that directly affect the IHB Program:

TDLR has adopted rules to implement this legislation which are effective March 15, 2020. You can read a summary and explanation of the rule changes here: https://www.tdlr.texas.gov/ihb/ihbjust.htm

2. What types of commercial buildings are regulated by the Texas Industrialized Housing and Buildings (IHB) program?

Historically the IHB program has covered buildings constructed in one or more modules at a location other than the installation site and designed to be used as a commercial structure when installed. The buildings are closed construction and cannot be inspected at the installation site without disassembling the building or destroying a portion of the building.

Changes to the IHB law added a new classification of buildings that are also covered by the IHB program. Effective January 1, 2010, portable classrooms designed for teaching the curriculum required by the Education Code, regardless of whether the construction is closed or not, are required to meet all the provisions that are required for industrialized buildings. These buildings are called “Relocatable Educational Facilities” or REFs.

3. Are there any commercial modular buildings that are not regulated by the IHB program?

Yes. Buildings that are regulated include permanent commercial structures and commercial structures designed to be transported from one commercial site to another commercial site, but do not include the following.

  1. A commercial building that is installed on a temporary foundation and that is either:
    1. not open to the public; or
    2. less than 1,500 square feet in total area and used as other than school or a place of religious worship.
  2. Construction site buildings. A construction site building is a commercial structure that is not open to the public and used for any purpose at a commercial site by a person constructing a building, road, utility, or other infrastructure or improvement to real property.

Note: Many relocatable commercial modular buildings that are less than 1,500 sf in size have been constructed and labeled under the Texas IHB program to help ensure acceptance by municipalities and because many municipalities want the assurance that the building has been constructed in compliance with the building codes. Relocatable buildings that are labeled under the Texas IHB program must comply with all requirements of the program, including compliance with the applicable building codes. The policies of a municipality with regard to buildings not labeled because they are exempt under the TX IHB statute are not covered under the Texas IHB statute or governed by IHB staff.

4. Are all portable buildings that are used as classrooms required to comply with the law?

Generally, yes. All portable classrooms that are manufactured are required to comply with the law. Portable classrooms that meet the definition of a site-built REF are also required to comply with the law. A site-built REF is a relocatable educational facility that is constructed at the first installation site and where the curriculum required under § 28.002 of the Education Code is taught. For additional questions, please contact us at (512) 539-5735 or IHBTech@tdlr.texas.gov.

5. My school district bought or leased non-certified site-built REFs prior to January 1, 2010. Can the school district renew the leases on these classrooms? Can the school district sell these classrooms to be used as classrooms?

No. Site-built REFs that do not bear an IHB certification decal may not be sold or leased as a REF on or after January 1, 2010. For additional questions, please contact us at (512) 539-5735 or IHBTech@tdlr.texas.gov.

6. What is a "man camp" Are modular buildings constructed for 'man camps' covered by the IHB law and rules?

'Man camp' is the term currently being used in the modular industry to describe buildings constructed for use of employess of companies involved in oil and gas exploration. These are generally transient lodging buildings and related structures such as dining facilities, commercial kitchens, laundry rooms, and recreation buildings.

Yes, these buildings are generally covered by the IHB law and rules unless they meet the exemptions in §1202.001 through 1202.003. TDLR has prepared a PowerPoint presentation that outlines the requirements of the IHB law and rules as they apply to these buildings. The PowerPoint presentation can be viewed online. The presentation is also available for download as a PDF (963 KB).

7. Is housing covered by the IHB program? What is the difference between an “IHB” or industrialized (modular) house and a manufactured house?

Yes, housing is covered by the IHB program. Industrialized housing is defined in § 1202.002 of the Occupations Code as a residential structure designed for the occupancy of one or more families and constructed in one or more modules built at a location other than the permanent site. The modules are designed as a permanent residential structure and are installed on a permanent foundation. Only housing designed as single-family housing, duplexes, townhouses, or apartments are considered industrialized housing. Residential occupancies such as dormitories and motels or hotels would be considered industrialized buildings, not industrialized housing.

The primary differences between industrialized housing and manufactured housing are as follows.

8. My house has a chassis—doesn’t this mean it’s a manufactured house?

No, a chassis does not make the house a manufactured house. As long as the construction of the industrialized house complies with the mandatory building code, the house may be constructed of any materials allowed by the code. Industrialized (modular) housing may be constructed with a steel chassis.

Unlike site built housing, industrialized housing requires a means of transport to move the house to the installation site. In many cases, the house is designed with the means of transport, in this case the chassis or steel frame, as a structural component of the house. A chassis that is designed to remain with the house is required to comply with all applicable sections of the mandatory building code. However, the house must be installed without the towing hitch, axles, brakes, wheels, and other parts of the chassis that operate only during transportation and are only there to facilitate transportation of the house.

9. What is the difference between an IHB manufacturer and an industrialized builder?

An IHB manufacturer is a person who constructs or assembles modules or modular components at a manufacturing facility. The modules or modular components are offered for sale or lease, sold or leased, or otherwise used.

An industrialized builder is a person who is engaged in the assembly, connection, and on-site construction and erection of modules or modular components at the building site. Alternately, an industrialized builder is a person who is engaged in the purchase of industrialized housing or buildings, modules, or modular components from a manufacturer for sale or lease to the public. A subcontractor of an industrialized builder does not have to be registered as an industrialized builder.

10. What is the difference between an IHB manufacturer and a REF builder?

A REF builder is a person who constructs a Relocatable Educational Facility (REF) at the first installation site. A person who constructs REFs in a manufacturing facility is not a REF builder, but a manufacturer. A person who assembles site-built REFs after the first installation is an industrialized builder.

11. What is the difference between an industrialized builder’s registration and an installation permit?

Manufacturers cannot release an industrialized house or building to a person who does not have either an industrialized builder registration or an installation permit issued by the Department.

A person who is a retailer of industrialized housing or buildings, or who is responsible for the assembly, connection, and on-site construction and erection of an industrialized house or building for persons other than themselves, must be registered as an industrialized builder. Subcontractors do not require the registration unless required by other applicable state laws. For example, electricians, HVAC contractors, and plumbers must be licensed in accordance with the applicable state law.

If you are purchasing or leasing an industrialized house or building for your own use, or your company's use, you may file for an installation permit in lieu of registering as an industrialized builder.

12. I am purchasing an industrialized house and want to build my own deck. Do I have to be registered as an industrialized builder?

No, you do not have to be registered as an industrialized builder. If you are purchasing the house for your own use (you will live there), then you will need to file an application for a residential installation permit with the Department. You will describe the construction for which you will be responsible on the permit application. A copy of the permit application may be downloaded from our web site.

13. The local building official says that I need an IHB decal. How do I get one?

If the housing or building is already constructed it is too late to obtain IHB decals or insignia for the modules or modular components that make up the house or building. If the housing or building has not yet been constructed, then you may contact one of the Texas registered industrialized builders (retailers/installers) or certified (approved) Texas IHB manufacturers to purchase your building. If the building has not yet been constructed and is a site-built REF, then the builder must register as a REF builder and the municipality will be responsible for the inspections.

A list of industrialized builders, a list of certified manufacturers, and a list of REF builders are available on our web site in PDF format. Manufacturers that wish to become certified under the Texas IHB program may download an information packet.

14. Can industrialized housing be installed on a temporary foundation? What is the difference between a "permanent" foundation and a "temporary" foundation?

No, industrialized housing cannot be installed on a temporary foundation system.

Generally, a "permanent" foundation is a foundation system with the following characteristics.

A temporary foundation typically consists of tie downs and anchors consistent with the foundation systems employed for manufactured housing. The Texas Industrialized Building Code Council (Council) permits the use of temporary foundation systems for industrialized buildings subject to the acceptance of the approving agency. The documents, plans, and specifications for a temporary foundation system must include the following:

Design review agencies may approve temporary foundation systems in compliance with the above, but the local authorities have the final say on what foundation system is appropriate for the installation site. The Council does not wish to force acceptance of a temporary foundation system where the building is to be placed in a permanent location, but determined that these systems may be adequate where a building is placed at a temporary location.

15. Chapter 1202 of the Occupations Code adopts the National Electrical Code, the Uniform Building Code group, and the Standard Building Code group as they existed on January 1, 1985, but the construction documents for modular housing and buildings installed within my jurisdiction indicate compliance with a later edition of the National Electrical Code (NEC) and the International Codes (I Codes). Is this legal?

Yes. § 1202.152 of the Occupations Code, Industrialized Housing and Buildings, grants authority to the Texas Industrialized Building Code Council (Council) to adopt later editions of the codes adopted in § 1202.151. The mandatory building codes currently in effect may be found in Department rule 70.100 and 70.101. § 70.100(c) provides the effective dates for past code editions adopted by the Council.

16. Where can I obtain a copy of the mandatory building codes adopted under the Texas Industrialized Housing and Buildings program?

The mandatory building codes adopted under the Texas Industrialized Housing and Buildings program are published by the International Code Council (ICC) and can be purchased from the ICC. For more information visit the ICC web site.

The mandatory building codes currently in effect can be found on our web site at http://www.tdlr.texas.gov/ihb/codes.htm .

17. Can a municipality prohibit buildings constructed under the IHB program from being placed inside their city limits or restrict these buildings to an area zoned for manufactured housing? If not, what authority do the municipalities have over IHB buildings?

No. There are areas of authority belonging to municipalities that are specifically and entirely reserved to them. However, the local requirements and regulations and others not in conflict with the IHB law or other state law relating to transportation, erection, or installation, or use, shall be reasonably and uniformly applied and enforced without distinction as to whether the housing or buildings are manufactured under the IHB program or are constructed on site.

In other words, a municipality must accept buildings that have been constructed under the Texas Industrialized Housing and Buildings program. If an area is zoned single-family residential, then the municipality must accept a single family residential IHB building in that area. If an area is zoned commercial, then the municipality must accept a commercial IHB building in that area. A municipality may enforce all local ordinances and zoning requirements that are not in conflict with the requirements of the IHB law.

A municipality may not require or enforce any amendments to the mandatory state codes for industrialized housing and buildings as a prerequisite for granting construction permits or certificates of occupancy. Additionally, a municipality must accept industrialized buildings as compliant with the current mandatory building code adopted under the Texas IHB program if the building has not been altered from the original plans (reference §1202.1535 of the Texas Occupations Code). Buildings that are altered may be recertified under the Texas IHB program. Once recertified the buildings must be accepted by municipalities as in compliance with the current mandatory building code adopted under the Texas IHB program.

The IHB law also grants municipalities more authority over industrialized housing provided that the municipality adopts ordinances. For example, a municipality may adopt an ordinance to require single family industrialized housing to have a value equal to or greater than the median taxable value for each single-family dwelling located within 500 feet of the proposed installation site.

More information concerning the areas of authority of municipalities may be found on our web site.

18. How do I transfer the title to my industrialized house or building?

There are no provisions in Chapter 1202 of the Occupations Code for the Department to issue or transfer titles for industrialized housing and buildings. Unlike manufactured housing, permanently installed industrialized housing or buildings are generally considered part of the real property and titles of ownership are provided the same as with site built housing and buildings.

19. Can I have my portable building recertified if it is altered? Is the altered building required to meet the mandatory building codes currently adopted under the IHB program?

Yes, if the building bears an IHB certification decal. Portable buildings that bear an IHB certification decal may be recertified if altered. Procedures for recertifying an existing industrialized building may be downloaded from our web site.

A portable building that does not have an IHB decal cannot be recertified under the Texas program.

The alterations must comply with the edition of the International Existing Building Code that is currently adopted by the Texas Industrialized Building Code Council. The effective edition of the code may be found on our web site.

For additional questions, please contact us at (512) 539-5735 or IHBTech@tdlr.texas.gov.

Licensing Questions

1. Can I apply for an installation permit for the installation of an industrialized house that will then be sold as real estate with the property on which it is installed?

No. An installation permit can only be obtained for the purchase and installation of an industrialized house if you plan to live in the house after it is installed. The intent of an installation permit was to give some relief from the registration requirements for an industrialized builder to a person who wants to purchase an industrialized house to live in and who is willing to take responsibility for the foundation and installation of the house.

2. Why do I have to give you my social security number when applying for registration?

In order to comply with the laws relating to child support enforcement under Parts A and D of the federal Social Security Act (42 U.S.C. Sections 601-617 and 651-669), Texas Family Code Section 231.302(c)(1) requires Texas State licensing agencies to obtain the social security numbers of all persons requesting a license or registration. Please be assured that the furnishing of social security numbers will be for the limited purpose of complying with the Family Code Section 231.302(c)(1). This information will not be used for any other purpose or made available to any other individual, organization or entity. Under Texas Attorney General Open Records Opinion No. 622 (January 27, 1994) even an open records request will not force us to release such information.

3. Does the Texas IHB program have reciprocity with any other state modular construction program?

No, the Department does not currently have reciprocity with any other state modular construction programs. Please see the IHB web site at http://www.tdlr.texas.gov/ihb/ihbreciprocity.htm for more information about reciprocity with other states.

4. How does a manufacturer become a certified (approved) industrialized housing and buildings manufacturer for Texas?

A manufacturer's information packet may be downloaded from our website at www.tdlr.texas.gov/IHB/041IHB.htm . A flow chart showing the steps to becoming a certified IHB manufacturer is available online in PDF format. A checklist of the pre-certification requirements that must be fulfilled prior to the start of a Texas certification inspection may be found at www.tdlr.texas.gov/IHB/pdf/019ihb.pdf.

5. How much does it cost to renew my registration?

NOTE: All fees submitted are non-refundable.

If your registration has been expired for more than 18 months but less than three years, you may submit a “Request to Executive Director for Expired License Renewal” form with the required renewal fee.

If your registration has been expired for more than three years you may not renew your registration. You must apply for a new registration.
You may be subject to enforcement actions, including administrative penalties and sanctions, for operating with an expired registration (expired less than 18 months) or operating without a registration (expired 18 months or more).

If your renewal application is postmarked before your expiration date, it is considered a timely renewal.

6. Who signs the application for registration for Manufacturers and Builders?

If the application is for a partnership, the signature must be one of the managing partners. If the application is for a corporation, the application must be signed by one of the officers of the corporation submitted on the application.

Enforcement Questions

1. How do I file a complaint against a licensee?

You may file a complaint online from our website or contact the department at 800-803-9202 (Texas only) or 512-463-6599.

Communication Questions

1. How may I receive notification of new and changing information with your department?

You may sign up on the TDLR E-mail Subscriber Notification Lists. These list(s) were established to allow subscribers to receive automated notification of new and changing information. To include yourself in the TDLR e-mail notification list(s), follow the instructions on the page.